Line balancing: a worked example with nine tasks

Line balancing splits the work needed for one unit across stations so that each station finishes within the takt time, using as few stations as possible. This guide takes nine real-looking tasks, finds the theoretical minimum, builds a balance, and then shows how task order changes the answer.

Worked example: the setup

A workshop makes steel shelf brackets. Available time is 450 minutes per shift and demand is 540 brackets, so the takt time is 50 seconds. The work for one bracket, in the order it is normally done:

TaskTime (s)
Cut22
Drill18
Deburr12
Weld35
Grind15
Paint prep20
Assemble28
Inspect14
Pack16
Total work content180

Step 1: the theoretical minimum number of stations

Minimum stations = total work content / takt time, rounded up = 180 / 50 = 3.6 → 4

No arrangement can do it with fewer than 4 stations. Check that no single task is longer than takt: the longest, Weld, is 35 seconds, so it fits.

Step 2: assign tasks to stations

A simple rule that works well: take the longest remaining task and put it in the first station where it still fits within takt. Repeat until all tasks are placed. This is called first-fit decreasing, and it is what the calculator on this site uses.

StationTasksLoad (s)Idle (s)
1Weld (35), Grind (15)500
2Assemble (28), Cut (22)500
3Paint prep (20), Drill (18), Deburr (12)500
4Pack (16), Inspect (14)3020

4 stations, matching the theoretical minimum. Three stations are loaded to exactly 50 seconds and the last carries 30.

Step 3: efficiency and balance delay

Line efficiency = total work content / (stations × takt) = 180 / (4 × 50) = 90% Balance delay = 1 − efficiency = 10%

10% of paid station time is idle, all of it at station 4. That is a good balance. In practice the idle time at the last station is a place for a part-time operator or for absorbing small disruptions.

Step 4: respect the task order

The balance above ignores sequence. It puts Assemble and Cut together, even though cutting happens first and assembly near the end. If parts must flow strictly in the listed order, each station can only take the next tasks in line:

StationTasksLoad (s)
1Cut, Drill40
2Deburr, Weld47
3Grind, Paint prep35
4Assemble, Inspect42
5Pack16

Now the line needs 5 stations and efficiency falls to 72%. The order constraint costs a whole station. To get back to 4, look for tasks that do not really depend on each other. Cutting and drilling blanks could run ahead in a separate cell, or inspection could be split between the stations that create each feature. The 4-station answer is the target; the sequence is where you negotiate.

Common mistakes

  • Ignoring precedence. A balance that puts dependent tasks in the wrong order is not a balance. Use the unconstrained result as a lower bound, then check the sequence on the floor.
  • Using average task times with large spread. If a task varies between 20 and 40 seconds, a station loaded to exactly takt will often run late. Leave a margin on variable tasks.
  • Forgetting walking and handling time. Moving the part, picking up tools and reaching for components belong in the task times.
  • Balancing once. When demand changes, takt changes, and so does the best split. Rebalance when demand moves by more than about 10%.
  • A task longer than takt. No assignment fixes that. Split the task, run two stations in parallel, or speed it up.

Run your own numbers

The free Takt Time & Line Balancing Calculator does this math as you type and shows each step. No sign-up, and your numbers stay in your browser.

Frequently asked questions

How do I calculate the minimum number of workstations?

Divide the total task time for one unit by the takt time and round up. 180 seconds of work at a 50-second takt gives 3.6, so at least 4 stations.

What is line efficiency?

Total work content divided by (number of stations × takt time). It shows what share of paid station time is spent on actual work. 100% means no station ever waits.

What is balance delay?

The idle share of station time: 1 minus line efficiency. A balance delay of 10% means one second in ten is spent waiting.

What is the best line balancing method?

For small problems, heuristics like longest-task-first or ranked positional weight get close to optimal quickly. For large lines with many precedence rules, specialised software or integer programming finds better answers.

Why does my real line need more stations than the formula says?

Usually task order, tasks tied to a specific machine or location, or tasks that cannot be split. The formula gives a lower bound that ignores those limits.