Reorder point formula: when to order, with worked examples
The reorder point is the stock level that tells you to place the next order. Get it right and the delivery arrives just as the shelf gets low. Here is how to calculate it in three steps, from the simplest version to one that copes with late suppliers.
The idea in one sentence
Order when the stock you have left is just enough to cover what you will sell while you wait for the delivery, plus a buffer for bad luck.
Worked example: a pharmacy item
A pharmacy sells a common pain reliever. Daily sales average 18 packs with a standard deviation of 5 packs. The distributor delivers 7 days after the order, and has been reliable. The pharmacist wants a 97.5% chance of not running out before each delivery, so z = 1.96.
Version 1: no buffer at all
If sales were exactly 18 every day, the reorder point would be the lead-time demand: 18 × 7 = 126 packs. Order when stock hits 126, and the last pack sells as the delivery comes in. In real life that means running out about half the time, because half the weeks are busier than average.
Version 2: add safety stock for uneven sales
Safety stock = 1.96 × 5 × √7 = 1.96 × 5 × 2.646 = 25.93, so 26 packs.
Reorder point = 126 + 26 = 152 packs.
Version 3: the distributor starts arriving late
Say deliveries now take 7 days on average but swing by 2 days either way (standard deviation 2). The buffer has to cover both uneven sales and the late truck:
Safety stock = 1.96 × √(7 × 5² + 18² × 2²) = 1.96 × √1,471 = 1.96 × 38.35 = 75.2, so 76 packs.
Reorder point = 126 + 76 = 202 packs.
The unreliable delivery almost triples the buffer, from 26 to 76 packs. That is 50 extra packs on the shelf all year, paid for by a supplier who cannot keep a date.
How to use it day to day
- Write the reorder point next to each item in your stock list.
- Each time you count or sell, compare the stock with the reorder point.
- When stock falls to the reorder point or below, place an order of your usual size (or the EOQ).
- Recalculate every few months, or whenever sales or the supplier change.
The order size and the reorder point are separate decisions. The reorder point decides when. The economic order quantity decides how much.
Common mistakes
- Looking only at what is on the shelf. Compare the reorder point with your inventory position: stock on hand plus anything already ordered but not yet delivered. Otherwise you will order twice for the same gap.
- Measuring lead time from the wrong moment. Lead time starts when you notice you need to order, not when the supplier confirms. Include the day or two it takes you to send the order and the time to put stock on the shelf.
- Counting weekly sales with a lead time in days. Convert everything to the same unit first.
- Rounding the buffer down. Always round safety stock and the reorder point up to a whole unit.
- Using the reorder point with infrequent counts. If you only check stock once a week, the formula needs the review period added to the lead time (L + review period), or you will often notice too late.
Run your own numbers
The free Safety Stock & Reorder Point Calculator does this math as you type and shows each step. No sign-up, and your numbers stay in your browser.
Frequently asked questions
What is the reorder point formula?
Reorder point = average daily demand × lead time in days + safety stock. With 18 units a day, a 7-day lead time and 26 units of safety stock, it is 126 + 26 = 152 units.
Can I calculate a reorder point without safety stock?
Yes: it is simply daily demand times lead time. But with no buffer you run out in roughly half of the delivery cycles, because sales are above average about half the time.
What lead time should I use?
The full time from deciding to order until the goods are ready to sell: preparing the order, the supplier’s processing, transport, receiving and shelving. If it varies, use the average and include its standard deviation in the safety stock.
How is reorder point different from EOQ?
The reorder point tells you when to order. EOQ tells you how much to order each time. You need both, and they are calculated separately.
What if I only count stock once a week?
Add the time between counts to the lead time when you calculate both the lead-time demand and the safety stock. A one-week review period on top of a seven-day lead time means planning for fourteen days.